单项选择题

An individual's willingness to take a risk can be determined by______.

A.decision tree modeling
B.monte Carlo method
C.sensitivity analysis
D.utility function
<上一题 目录 下一题>
热门 试题

单项选择题
Utility function is a commonly used technique to find out the tolerance of a project manager towards risk.Some project managers are more averse towards risk than others.All the following are different classifications of tolerance for risk EXCEPT______.
A.risk averter
B.risk seeker
C.risk mitigator
D.risk neutral
单项选择题
Of the following types of historical information that can be used in risk identification,which is the least reliable
A.Project file
B.Commercial database
C.Project team knowledg
D.Lessons learned database