单项选择题
Of the following types of historical information that can be used in risk identification,which is the least reliable
A.Project file
B.Commercial database
C.Project team knowledg
D.Lessons learned database
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
You are building a water treatment facility.Routine tests reveal that there are contaminants in the water but that they have an extremely low risk for causing any sickness.As the project manager,you should______.
A.inform the public that a detailed examination has been ordered to determine the extent to which the problem exists
B.do nothing because there is extremely low risk for sickness except for some effects on small children and the elderly
C.tell the public there is no problem,except for small children and the elderly who need to boil the water before drinking
D.educate the public about the advances on water treatment technology and the industry efficiency and safety record
点击查看答案&解析
单项选择题
You are in the process of developing options,and determining actions to enhance opportunities and reduce threats to the project's objectives.What should you be doing next
A.Determining which risks might affect the project and documenting their characteristic
B.Identifying,analyzing and planning for newly arising risk
C.Deciding how to approach and conduct risk management activities for the projec
D.Assessing the priority of identified risks using their probability of occurin
点击查看答案&解析
相关试题
The probability of failure for a p...
You are beginning a new project th...
You had budgeted $200000 in ...
In your project,you have identifed...
You are the project manager in an...