单项选择题
Output from the activity resource estimating process includes ______ .
A.job descriptions
B.salary schedules
C.identification and description of the types and quantities of resources required
D.analogous estimating
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A.PERT
B.CPM
C.parametric estimating
D.none of the above
点击查看答案&解析
单项选择题
All the following statements regarding creating of time estimates are correct EXCEPT:
A.Mathematical analysis like CPM, GERT and PERT indicate the dates in which the activity can be scheduled given resource limits and other constraint
B.Duration compression techniques including fast tracking and crashing can help in decreasing the project schedul
C.WBS classification allows for useful activity ordering and sortin
D.The duration of the project is the sum of durations for all the tasks in the projec
点击查看答案&解析
相关试题
You work for one of the leading m...
You are doing a Monte Carlo Analys...
Resource calendars affect a specific...
You work for an architectural-engin...
You have taken information on proje...