单项选择题

A planning package is a ______ .

A.unit of the project plan
B.unit of the scope management plan
C.WBS component below the control account
D.template used for the project
<上一题 目录 下一题>
热门 试题

单项选择题
Output from the activity resource estimating process includes ______ .
A.job descriptions
B.salary schedules
C.identification and description of the types and quantities of resources required
D.analogous estimating
单项选择题
In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A.PERT
B.CPM
C.parametric estimating
D.none of the above