单项选择题
A planning package is a ______ .
A.unit of the project plan
B.unit of the scope management plan
C.WBS component below the control account
D.template used for the project
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Output from the activity resource estimating process includes ______ .
A.job descriptions
B.salary schedules
C.identification and description of the types and quantities of resources required
D.analogous estimating
点击查看答案&解析
单项选择题
In your project, you are using most likely. optimistic and pessimistic activity duration estimates(for activity duration estimating). The technique that you are using is ______ .
A.PERT
B.CPM
C.parametric estimating
D.none of the above
点击查看答案&解析