单项选择题

Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is ______.

<上一题 目录 下一题>
热门 试题

单项选择题
Consumption of the total life-cycle effort in software maintenance is ______ that in software development.
A.less than
B.larger than
C.equal Or less than
D.equal or larger than
单项选择题
Which of the following is not part of a modern quality management concept ______
A.Performance standard is zero defects
B.Quality must be inspected in
C.85% of failures occur because of the process, not the worker
D.Quality is a 4 cycle process - plan/do/check/act