A project has the following characteristics: payback of $2,000, profit of $1,000, project cost of $800, life cycle cost of $1,200. What is the benefit cost ratio of the project

A.2.50.
B.1.25.
C.1.67.
D.0.83.
<上一题 目录 下一题>
热门 试题

单项选择题
Which of the following is NOT a part of the project management plan
A.Procurement management pla
B.Process improvement pla
C.Schedule baselin
D.Resource requirement pla
单项选择题
When developing the project charter, any kind of the organzation's enterprise environmental factors must be considered. This may include the following EXCEPT______.
A.company reputation
B.personnel administration procedure, including training records
C.existing facilities and capital equipment
D.stakeholder risk tolerances