单项选择题
A project has the following characteristics: payback of $2,000, profit of $1,000, project cost of $800, life cycle cost of $1,200. What is the benefit cost ratio of the project
A.2.50.
B.1.25.
C.1.67.
D.0.83.
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Which of the following is NOT a part of the project management plan
A.Procurement management pla
B.Process improvement pla
C.Schedule baselin
D.Resource requirement pla
点击查看答案&解析
单项选择题
When developing the project charter, any kind of the organzation's enterprise environmental factors must be considered. This may include the following EXCEPT______.
A.company reputation
B.personnel administration procedure, including training records
C.existing facilities and capital equipment
D.stakeholder risk tolerances
点击查看答案&解析
相关试题
A project manager is working on a...
Your project is in the planning ph...
Managing e-business projects for th...
Your project is very critical for ...
Although your internet start-up com...