Which of the following is NOT a part of the project management plan
A.Procurement management pla
B.Process improvement pla
C.Schedule baselin
D.Resource requirement pla
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
When developing the project charter, any kind of the organzation's enterprise environmental factors must be considered. This may include the following EXCEPT______.
A.company reputation
B.personnel administration procedure, including training records
C.existing facilities and capital equipment
D.stakeholder risk tolerances
点击查看答案&解析
单项选择题
A project should be terminated for all of the following reasons EXCEPT:
A.Lack of team synerg
B.The project no longer meets the company's objective
C.The resources are not available to complete project activitie
D.Project funding has been significantly reduce
点击查看答案&解析
相关试题
A project manager is working on a...
Your project is in the planning ph...
Managing e-business projects for th...
Your project is very critical for ...
Although your internet start-up com...