单项选择题
Primary responsibility for establishing design and test specifications rests with ______ .
A.senior management
B.procurement
C.engineering
D.quality control
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Checklists are completed in which process
A.Risk identificatio
B.Quality assuranc
C.Quality plannin
D.Quality contro
点击查看答案&解析
单项选择题
A project manager needs to assess qualify on the project. To do so, he wants to measure the height of each table produced. However, that would be too expensive. In this case, it would be BEST to use ______ .
A.benchmarking
B.a sample
C.a control chart
D.a Pareto diagram
点击查看答案&解析
相关试题
A metric is an operational definiti...
An early version of one of W. Ed...
You are a project manager for resi...
A project team is in the design s...
You are trying to determine what c...