单项选择题
Checklists are completed in which process
A.Risk identificatio
B.Quality assuranc
C.Quality plannin
D.Quality contro
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
A project manager needs to assess qualify on the project. To do so, he wants to measure the height of each table produced. However, that would be too expensive. In this case, it would be BEST to use ______ .
A.benchmarking
B.a sample
C.a control chart
D.a Pareto diagram
点击查看答案&解析
单项选择题
Inputs to quality control include all of the following EXCEPT ______ .
A.work performance information
B.quality management plan
C.quality checklists
D.PERT chart
点击查看答案&解析