单项选择题
Which of the following is not estimate costs tool or technique
A) Historical relationships.
B) Analogous.
C) Bottom-up.
D) Parametric.
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Inputs to determine budget include all of the following EXCEPT ______ .
A) cost baseline
B) cost estimate
C) work breakdown structure
D) project schedule
点击查看答案&解析
单项选择题
The measure used to forecast project cost at completion is ______ .
A) CPI
B) SPI
C) BCWP
D) ACWP
点击查看答案&解析
相关试题
In your project, there have been ...
One common way to compute estimated...
The cost reserve should be ____...
During execution, a functional mana...
The estimate at completion (EAC) ...