单项选择题
The measure used to forecast project cost at completion is ______ .
A) CPI
B) SPI
C) BCWP
D) ACWP
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
All of the following are examples of tools often used in estimate costs EXCEPT ______ .
A) parametric modeling
B) analogous estimating
C) bottom-up estimating
D) activity duration estimates
点击查看答案&解析
单项选择题
Cost control outputs include all of the following EXCEPT ______ .
A) estimate at completion
B) budget updates
C) revised cost estimates
D) cost baseline
点击查看答案&解析