单项选择题

The measure used to forecast project cost at completion is ______ .

A) CPI
B) SPI
C) BCWP
D) ACWP
<上一题 目录 下一题>
热门 试题

单项选择题
All of the following are examples of tools often used in estimate costs EXCEPT ______ .
A) parametric modeling
B) analogous estimating
C) bottom-up estimating
D) activity duration estimates
单项选择题
Cost control outputs include all of the following EXCEPT ______ .
A) estimate at completion
B) budget updates
C) revised cost estimates
D) cost baseline