单项选择题

After preparing the probability distribution of cost outcome for a project, the estimate, with a 15% probability of being exceeded, is approximately one standard deviation ______ .

A) below the mean
B) above the median
C) above the mean
D) above the median
<上一题 目录 下一题>
热门 试题

单项选择题
Rebaselining may be required in cost control when ______ .
A) CVs are severe, and a realistic measure of performance is needed
B) revised cost estimates are prepared and distributed to stakeholders
C) corrective action must be taken to bring expected future performance in line with the project plan
D) EAC shows that additional funds are needed to complete the project even if a scope change is not needed
单项选择题
As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ______ .
A) performance reviews
B) variance analysis
C) trend analysis
D) earned value management
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...