单项选择题

As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ______ .

A) performance reviews
B) variance analysis
C) trend analysis
D) earned value management
<上一题 目录 下一题>
热门 试题

单项选择题
The cost management plan has all of the following characteristics EXCEPT:
A) It is based on the project cost estimates, and is separate from the project plan.
B) Can establish variance thresholds for costs or other indicators.
C) May be formal or informal, highly detailed or broadly framed.
D) Documents the cost management processes and their associated tools and techniques.
单项选择题
A project was expected to cost $6 million for 3 months. At the end of 1 month, you use earned value as a performance management tool and get the following information: BCWP=$1.5 million, BCWS=$2.5 million, ACWP=$2.2.million. What is the schedule variance
A) $0.3 million.
B) $-1 million.
C) $1 million。
D) $0.7 million.
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...