A management control point can be placed at selected management points (specific components at selected levels)of the WBS above. the work package level. These control points can be ______ .
A) used for rolling wave planning B) decomposed further to help in creation of work authorization system C) used for planning known work content that does not have detailed schedule activities D) used as a basis for planning when associated work packages have not yet been planned