单项选择题

()is not the tool name for quality controlling used in the figure below.

A.Cause and Effect Diagrams
B.Ishikawa Diagrams
C.Fishbone Diagrams
D.Scatter Diagram

<上一题 目录 下一题>
热门 试题

单项选择题
()is one of the techniques used for estimating activity durations.

A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates

单项选择题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. () is following the process- Estimate Activity Durations.

A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities