单项选择题

()is one of the techniques used for estimating activity durations.

A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates

<上一题 目录 下一题>
热门 试题

单项选择题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. () is following the process- Estimate Activity Durations.

A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities

单项选择题
One tool that is useful during both analysis and design is the(),which is a pictorial representation of the items of information(entities) within the system and the relationships between these pieces of information.

A.data dictionary
B.dataflow diagram
C.use case diagram
D.entity-relationship diagram