单项选择题

Outputs from risk response planning include all of the following EXCEPT______.

A.risk register updates
B.corrective actions
C.risk-related contractual agreements
D.project management plan updates
<上一题 目录 下一题>
热门 试题

单项选择题
While implementing your project,a team member brings to your notice a risk that was not mentioned in the risk response plan.In this case,you should______.
A.accept the risk
B.perform additional risk response planning to control the risk
C.inform the project sponsor
D.use project contingency
单项选择题
The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.Where could the found to cover the newly discovered work item
A.Contingency reserv
B.Project profi
C.Management reserv
D.Abandoning fun