单项选择题

The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.Where could the found to cover the newly discovered work item

A.Contingency reserv
B.Project profi
C.Management reserv
D.Abandoning fun
<上一题 目录 下一题>
热门 试题

单项选择题
In your project,there is:50% probability for $40000 profit,50% probability for $25000 loss.What is the expected profit in your project
A.$32500.
B.$25000.
C.$7500.
D.-$7500( loss of $7500).
单项选择题
All the following are purposes of project risk management EXCEPT______.
A.identifying factors that are likely to affect the project scopquality,time and cost
B.developing response strategies for all identified risks
C.providing a baseline for project factors that cannot be controlled
D.mitigating impacts by influencing project factors that can be controlled
相关试题
  • The probability of failure for a p...
  • You are beginning a new project th...
  • You had budgeted $200000 in ...
  • In your project,you have identifed...
  • You are the project manager in an...