Which of the following techniques is used for tracking the project risks?()

A.Probability-Impact matrix
B.Pareto chart
C.R-Chart
D.PERT (Program Evaluation and Review Technique) analysis

<上一题 目录 下一题>
热门 试题

单项选择题
WhichistheMOSTeffectivemethodforgeneratingsupportforyourprojectplan?()

A.Requiring stakeholders to sign-off on project plan components
B.Requesting input from all stakeholders during the planning process
C.Providing an open line of communication regarding the project
D.Clearly illustrating how the project relates to the company’s objectives

单项选择题
Whichfactorhasthegreatestimpactontheestimatedperunitlaborcostforaproject?()

A.Historical information
B.Use of outside vendors
C.Change control processes
D.Human resource skill level requirements