单项选择题

Why does a project manager need an executive sponsor?()

A.To keep the project team focused on its work
B.To provide behind-the-scenes assistance with organizational commitment and support
C.To sign-off on user requirements
D.To negotiate contracts with outside vendors

<上一题 目录 下一题>
热门 试题

单项选择题
Theprojectmanagerisdevelopingaprojectschedule.Theprojectmanagernegotiatedwithalltheexecutionorganizations,andthetasktimesareasshortaspossible.Aftermanipulatingtheschedule,theprojectcompletiondateisstillbeyondthedaterequestedbythebusinessownersoftheproject.Theprojectmanagerbelievesthatthecontentagreedonfortheprojectisappropriate,andconcludesthatthisscheduleshouldbetakentothebusinessownersandrenegotiated.Whichoneofthefollowingtoolswillhelptheprojectmanagerjustifytherevisedschedule?()

A.Data flow model
B.The project critical path
C.Resource loading chart
D.WBS (Work Breakdown Structure)

单项选择题
WhatistheMOSTaccuratewaytodetermineaproject’sdurationbeforeexecution?()

A.The project manager performs all estimates
B.Incorporate each individual worker’s estimates
C.Acquire expert estimates
D.There is no way to determine the duration

相关试题
  • Teamselectionisnotjustafunctionoffinding...