单项选择题
The following diagram denotes dependency between two activities A and B,It says()
A.B can’t start before A is finished B.B can’t finish before A is finished C.B can’t start before A starts D.B can’t finish before A starts
A.relationships B.resources C.stakeholders D.deliverables
A.work breakdown structure B.baseline C.software requirements specification D.plan