On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and (70) are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating B.cost estimating C.project planning D.schedule development