I Which project management process group is managing stakeholders in

A.Initiatin
B.Plannin
C.Executin
D.Monitoring and controllin
<上一题 目录 下一题>
热门 试题

单项选择题
Statements of organizational policies and philosophies,position descriptions,and constraints are examples of______.
A.downward communication
B.lateral communication
C.external communication
D.horizontal communication
单项选择题
You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______.
A.all stakeholders in the performing organization
B.all project stakeholders
C.project team members and the project sponsor
D.people noted in the communications management plan
相关试题
  • You finally have been appointed pro...
  • You have decided to organize a stu...
  • Your company CEO just sent you an...
  • In your project,you conducted commu...
  • You are managing a project to deve...