单项选择题
Risk response development is intended to______.
A.create steps to identify project risks
B.formulate strategies for dealing with adverse events
C.construct a list of previous project risks
D.develop measurements to quantify project risks
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Charles is working on a project and finds that one of his primary vendors is raising their costs for a key component of the product being produced by his project.In order to cover these costs,he______.
A.will ask management for a budget increase to cover the difference
B.will assume management reserve will cover the difference because this increase was out of his control
C.will use the cost change control process to obtain approval to use part of the contingency allowance
D.will go over budget and ask for forgiveness at the end of the project Charles
点击查看答案&解析
单项选择题
Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives.Risk response planning helps in this context because it______.
A.helps in deciding how to approach and plan the risk management activities
B.develops procedures and techniques to enhance opportunities and reduce threats to project objectives
C.determines which risks might affect the project and documents their characteristics
D.monitors residual risks,identifies new risks and executes risk reduction plans
点击查看答案&解析