Which of the following is not related to control process groups

A.Team developmen
B.Quality contro
C.Benefit cost analysi
D.Verify scop
<上一题 目录 下一题>
热门 试题

单项选择题
Which of the following projects(i.e.Project A, Project B or Project C) should be selected
A.Project A with opportunity cost of $100,000 and investment of $1,000,000.
B.Project B with opportunity cost of $200,000 and investment of $500,000.
C.Project C with opportunity cost of $300,000 and investment of $3,500,000.
D.Cannot be determined with available informatio
单项选择题
As part of monitoring and controlling, project performance must be monitored and measured regularly to identify variances from the plan. All the following are processes involved with controlling EXCEPT______.
A.verify scope
B.risk monitoring and control
C.performance reporting
D.quality assurance
相关试题
  • A project manager is working on a...
  • Your project is in the planning ph...
  • Managing e-business projects for th...
  • Your project is very critical for ...
  • Although your internet start-up com...