International factors to be considered by the project team generally include all of the following EXCEPT:
A.Time zone difference
B.National and regional holiday
C.Travel requirements for face-to-face meeting
D.Project reporting format
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Co-location is one of the tools and technique to ______ .
A.plan the organizational structure
B.develop the project team
C.acquire the project team
D.plan the project resources
点击查看答案&解析
单项选择题
While managing projects, negotiating helps in conferring with others to come to terms with them or reach an agreement. A form of assisted negotiation is ______ .
A.arbitration
B.problem solving
C.regulation
D.compromising
点击查看答案&解析