单项选择题
Of the following estimates, which most accurately reflect the actual cost of the project
A) Conceptual estimates.
B) Order of magnitude estimates.
C) Preliminary estimates.
D) Bottom-up estimate.
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
A generally accepted method to confirm accuracy of task progress is through ______ .
A) earned value
B) probability vs. outcome
C) maximum ceiling
D) work breakdown structure
点击查看答案&解析
单项选择题
A recommended corrective action is an output of which cost management process area
A) Resource planning.
B) Cost estimating.
C) Cost budgeting.
D) Cost control.
点击查看答案&解析
相关试题
In your project, there have been ...
One common way to compute estimated...
The cost reserve should be ____...
During execution, a functional mana...
The estimate at completion (EAC) ...