单项选择题

Tool for defining activities is ().

A.Dependency Determination
B.Precedence Diagramming method
C.Rolling Wave Planning
D.Schedule network Templates

<上一题 目录 下一题>
热门 试题

单项选择题
Changes often happen in ().

A.initiating process
B.Executing process
C.Planning Process
D.Closing Process

单项选择题
() is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

A.PERT
B.AOA
C.WBS
D.PDM