单项选择题
Communications technology factors that can affect the project include all of the following EXCEPT______.
A.the length of the project
B.the availability of technology
C.executive requirements
D.the urgency of the need for information
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
During a meeting to negotiate a change to the contract,the seller states that they have another meeting at three p.m.Negotiations will have to be over by then.What kind of negotiation technique is this
A.Deadlin
B.Missing ma
C.Deman
D.Dela
点击查看答案&解析
单项选择题
The process of performance reporting includes all of the following except______.
A.status reporting
B.progress reporting
C.forecasting
D.product analysis
点击查看答案&解析