单项选择题
在管理项目时,你发现预计的项目完工时间将超出期望的日期,你首先应该( )。
A.向项目增加资源
B.评估同时进行更多活动的可能性
C.向管理层要求延长工期
D.对项目进行赶工
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
You are assigned as the project manager in a project with an aggressive schedule. During a recent meeting your team complained about the high pressure applied and the many hours of overwork time. What should you do first
A) Try to obtain additional budget and time.
B) Improve team communication and availability of high quality data on risks. Use this information to enable you to make well-founded decisions earlier.
C) The problem might be the customer disturbing project rhythm. Keep him on distance from the team.
D) Apply fast tracking to shorten project duration without additional work.
点击查看答案&解析
单项选择题
Which of the following is not a tool & technique of the develop project charter process
A) Earned value method.
B) Project selection methods.
C) Project management information system.
D) Project management methodology.
点击查看答案&解析
相关试题
Which of the following statements i...
某个跨部门的开发项目,采用矩阵型组织结构...
项目管理办公室(PMO)的主要职能通常包括...
在控制范围过程中,需要评估实际项目范围偏...
Company procedures require the creat...