Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance
A) Consider overtime work as part of the job. B) Prepare a cost baseline. C) Use earned value management to monitor performance. D) Estimate and budget controllable and uncontrollable costs separately.