Completion of project scope activities is not measured against the ______ .

A.scope statement
B.requirements
C.WBS dictionary
D.WBS
<上一题 目录 下一题>
热门 试题

单项选择题
The causes of variances and the reasoning behind the corrective action chosen are summarized the ______ .
A.work breakdown structure
B.accounting codes for the activities
C.lessons learned
D.performance reports
单项选择题
In your project, you use product analysis to translating project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT ______ .
A.value engineering
B.value analysis
C.product breakdown
D.benefit/cost analysis