单项选择题

At the first phase end of the project, you should ensure that ______ before you begin the next phase.

A.resource are available for the next phase
B.progress was achieved to its baseline
C.corrective actions are taken to bring project results
D.the phase has achieved the objectives and formally accepts its deliverables