Several risk response strategies are available. ______ the risk simply gives another party responsibility for its management, it does not eliminate risk.
A. Avoiding
B. Mitigating
C. Accepting
D. Transferring
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
The project budget has been finalizeD.Additional work has been discovered that was not planned for in the budget or project scope. () could provide the fund to cover the newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
点击查看答案&解析
单项选择题
Quality managemen ______.
A.is another name for careful inspections
B.is inversely related to productivity
C.is primarily the responsibility of management
D.is primarily the responsibility of the workers