单项选择题

The project manager has the lowest level of authority in a ______ organization.

A.functional
B.weak matrix
C.strong matrix
D.projectized
<上一题 目录 下一题>
热门 试题

单项选择题
As for projects and operational work, which of the followings is proper
A.A project is constrained by limited resources and operational works generally have no such constraint
B.Projects and operations differ primarily in that operations are ongoing, projects are temporar
C.Projects are different because the project conclueds when its specific objectives have been attained, while operations are repetitiv
D.Operational works are not defined as a projec
单项选择题
The first phase of a project is the feasibility study. According to the PMBOK, which of the project management process group does the feasibility study phase need
A.Plannin
B.Planning and monitoring & controllin
C.Initiating and closin
D.All of five process groups: initiating, planning, executing, monitoring & controlling, and closin
相关试题
  • Your company is going to start an...
  • You recently were assigned to a pr...
  • You are one of four full-time pro...
  • You have always dreamed of living ...
  • You are managing the construction o...