单项选择题

The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

<上一题 目录 下一题>
热门 试题

单项选择题
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements.

A.Plannlng
B.Executing
C.Monitoring and Controlling
D.Closing

单项选择题
()are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

A.Project manager
B.Project team member
C.Sponsor
D.Proiect stakeholders

相关试题
  • ()involves comparing actual or pla...
  • ()is the budgeted amount for the...
  • PDM includes four types of dependen...
  • The process of()schedule activity ...
  • The()describes,in detail,the proje...