单项选择题

Activity duration estimate inputs include all of the following EXCEPT ______ .

A.resource requirements
B.projeet document updates
C.activity lists
D.constraints
<上一题 目录 下一题>
热门 试题

单项选择题
To maintain the customer's schedule, massive overtime will be required between Christmas and new years. Many of your team members have put in for vacation during this time. You should ______ .
A.let the schedule slip and inform the customer
B.first give the employees the choice of working overtime
C.make the employees cancel their vacation plans and work overtime
D.hire temporary employees for the overtime
单项选择题
In what way does free float differ from total float
A.Free float is the amount of total float that does not affect the end date, whereas total float is the accumulated amount of free floa
B.There is no difference-the two terms are functionally equivalen
C.Free float is the amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities, whereas total float is concerned with delays that do not affect the project finish dat
D.An activity's free float is calculated by subtracting its total float from the critical path's total floa
相关试题
  • You work for one of the leading m...
  • You are doing a Monte Carlo Analys...
  • Resource calendars affect a specific...
  • You work for an architectural-engin...
  • You have taken information on proje...