单项选择题

In your project, you are in the process of determining whether the activities being done as part of your project comply with organizational and project policies. This will be done as part of ______ .

A.inspection
B.quality audit
C.quality improvement
D.trend analysis
<上一题 目录 下一题>
热门 试题

单项选择题
Identifying which quality standards are relevant to the project and determining how to satisfy them should be addressed during ______ .
A.the conceptual phase
B.the planning process
C.project implementation
D.risk identification
单项选择题
When it appears that a design error will interfere with meeting technical performance objectives, the PREFERRED response is to ______ .
A.decrease the performance value to equal the assessed value
B.develop alternative solutions to the problem
C.increase the specified value to set a new performance goal
D.reduce the overall technical complexity of the project
相关试题
  • A metric is an operational definiti...
  • An early version of one of W. Ed...
  • You are a project manager for resi...
  • A project team is in the design s...
  • You are trying to determine what c...