单项选择题

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved ()that can serve as a baseline to track progress.

A.scope statement
B.Activity list
C.project charter
D.Project schedule

<上一题 目录 下一题>
热门 试题

单项选择题
()is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

A.PERT
B.AOA
C.WBS
D.PDM

单项选择题
The project life-cycle can be described as()

A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting