单项选择题

In project network diagram,the number of critical path is().

A、none
B、only one
C、only two
D、one or more

<上一题 目录 下一题>
热门 试题

单项选择题
()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.

A、The project charter
B、The project scope statement
C、The WBS dictionary
D、The activity list

单项选择题
Validate Scope is the process of formalizing acceptance of completed().

A、project deliverables
B、WBS
C、activities
D、milestones