单项选择题

项目的控制图显示,最后10个部件的尺寸全部超过控制上限。项目经理应该怎么做?()

A.为偏差寻找非随机原因
B.对这些部件进行返工
C.立即停产
D.按ISO9000标准进行过程改进

<上一题 目录 下一题>
热门 试题

单项选择题
In your project, you want to monitor and control project processes associated with initiating, planning, executing and closing. This will help you take corrective or preventive action to control project performance. In this context, what should you do first ?()

A.Review all project forecasts
B.Detail all the activities of project team members involved in executing administrative closure for the project
C.Review the project management plan and work performance information for your project
D.Manage project risks

单项选择题
下列哪一项完成后才能编制详尽的项目进度计划?()

A.项目管理计划
B.工作分解结构
C.项目人力资源计划
D.项目成本预算