Given: BAC=200, AC=120, EV=80, CPI=0.666. Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is ______ .
A) 120
B) 160
C) 200
D) 240
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Which of the following is not estimate costs tool or technique
A) Historical relationships.
B) Analogous.
C) Bottom-up.
D) Parametric.
点击查看答案&解析
单项选择题
Inputs to determine budget include all of the following EXCEPT ______ .
A) cost baseline
B) cost estimate
C) work breakdown structure
D) project schedule
点击查看答案&解析