单项选择题
Responses to risk threats include all of the following except______.
A.avoidance
B.acceptance
C.mitigation
D.rejection
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Which of the following is not a disadvantage of using statistical approaches to quantify risk
A.Input data may be inaccurate and incomplet
B.Managers sometimes rely on computer-produced results that are detailed and impressive but inaccurate,which makes decision making difficul
C.Risk experts can understand the complex statistical approaches but they are not good at communicate with they kno
D.When applying in quantitative risk analysis,statistical approaches are regard as too theoretica
点击查看答案&解析
单项选择题
when is the greatest difference between risks or opportunities and investment at stake
A.Conceptio
B.Developmen
C.Implementatio
D.Closur
点击查看答案&解析
相关试题
The probability of failure for a p...
You are beginning a new project th...
You had budgeted $200000 in ...
In your project,you have identifed...
You are the project manager in an...