Risk transference nearly always involves______.
A.eliminating risk through beta testing
B.policies and procedures for a response system
C.accepting a lower profit if some activities overrun
D.payment of a risk premium to the party taking on the risk
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
An output of risk identification is______.
A.a risk register
B.expected monetary value of the risk events
C.corrective actions
D.the plan for mitigation
点击查看答案&解析
单项选择题
In your project,you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management.What could be a potential next step
A.Perform a structured review of project plans and assumptions,both at the total project and detailed scope level
B.Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar project
C.Conduct planning meetings to develop the risk management pla
D.Conduct interviews to quantify the probability and consequences of risks on project activitie
点击查看答案&解析