Cultural and social environmental aspects to be considered by the project team include all of the following areas EXCEPT ______ .
A.Economic
B.Occasional
C.Educational
D.Demographic
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Project management techniques applied to ongoing operations is called as ______ .
A.portfolio management
B.management by projects
C.management by objectives
D.management by exception