单项选择题
在进行项目风险定性分析时,一般不会涉及到(46);在进行项目风险定量分析时,一般不会涉及到(47)。
A.风险数据质量评估
B.风险概率和影响评估
C.风险紧急度评估
D.建模和仿真
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
点击查看答案
单项选择题
Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.
A.Integration
B.Time
C.Planning
D.Communication
点击查看答案