单项选择题

An output of scope definition is ______ .

A.work breakdown structure (WB
B.resource breakdown structure (RB
C.project scope statement
D.schedule delays control plan
<上一题 目录 下一题>
热门 试题

单项选择题
All of the following are examples of a source of scope change EXCEPT ______ .
A.a variation in government regulations
B.failure to include a required feature in the design of a telecommunication system
C.discovering a need to engage in bottom-up cost estimating
D.introducing technology that was not available when scope was originally defined
单项选择题
Reviewing work products and results to ensure that all were completed satisfactorily and formally accepted is part of ______ .
A.risk management
B.quality control
C.change control management
D.verify scope