单项选择题
The need for______is one of the major driving forces for communication in a project.
A.optimization
B.integrity
C.integration
D.differentiation
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
About midway through the project,the project manager learns that most members of the project team do not review the weekly project updates.What should the project manager do
A.Great a signature log do team members can indicate when they have read the report
B.Revise the communications plan appropriately to meet the information needs of the stakeholder
C.Improve the layout of the weekly project updates to encourage reading by team member
D.Go to the team members first hand to inquire why they are not reading the report
点击查看答案&解析
单项选择题
Extensive use of______communication is most likely to aid in solving complex problems.
A.verbal
B.written
C.formal
D.non-verbal
点击查看答案&解析
相关试题
You finally have been appointed pro...
You have decided to organize a stu...
Your company CEO just sent you an...
In your project,you conducted commu...
You are managing a project to deve...