单项选择题
All of the following choices represent inputs to the activity resource estimating process EXCEPT:
A.Organizational process asset
B.Activity lis
C.The actual final cost of the last projec
D.Enterprise environmental factor
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT ______ .
A.activities that are not required as part of project scope
B.activities that are to be performed as part of the project
C.activity identifier and scope of work description for each schedule activity
D.all the above are included in the activity list
点击查看答案&解析
单项选择题
All the following are benefits of fast tracking a project EXCEPT ______ .
A.facilitates duration compression
B.reduces risk
C.ensure activities are done in parallel which would normally be done in sequence
D.helps shorten the project schedule without changing the project scope
点击查看答案&解析
相关试题
You work for one of the leading m...
You are doing a Monte Carlo Analys...
Resource calendars affect a specific...
You work for an architectural-engin...
You have taken information on proje...