单项选择题

You are getting project performance information as your project is being executed. Based on the performance information, forecasts are updated and reissued. Some factors that could change as forecasts are updated include ______ .

A) estimate to complete
B) estimate at completion
C) estimate to complete and estimate at completion
D) none of the above
<上一题 目录 下一题>
热门 试题

单项选择题
You have recently taken over a new project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend ______ .
A) issuing budget updates
B) revising the cost baseline
C) corrective action e. g. adjusting schedule activity budgets
D) closing the project
单项选择题
While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects. You should ______ .
A) reject the estimate and remove the functional manager from the project
B) request the supporting details for the estimate to ensure it has been properly prepared
C) accept the estimate and plan to use the additional funding as a reserve
D) question each functional manager for information about this estimate
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...